Manchester Road Streetscape Phase 3

April 29, 2019

Ameren has completed most of their relocation work, except for the overhead crossings over Manchester Road.  ATT will be splicing the new conduit on the east end of the project over the next 2 months.  ATT will also have another contractor performing relocation work on the west end of the project over the next few months.  Spectrum has placed most of their new overhead line on the new Ameren poles and will be working on their underground connection work near Taylor Road in the next month.

March 29, 2019

Ameren has completed most of their relocation work, except for the overhead crossings over Manchester Road.  Conduits will be installed at nine locations under Manchester this spring and the overhead electric and cable crossings will be moved undergound over the next few months as weather allows.  ATT will also continue relocation work over the next few months as weather allows.

February 8, 2019

Several of the utility companies have begun their relocation work on this project.   Ameren will be relocating poles and moving lines over the next few months as weather allows.  Missouri American Water Company and ATT will also be relocating facilities over the next few months in preparation for the Streetscape Improvements.

Project Overview

Phase 3 includes the section of Manchester Road between Taylor Road and Eatherton Road, and will incorporate similar improvements to those recently constructed during Phases 1 and 2 to the east and west of this project.  The project will incorporate vehicular lanes, bike lanes, sidewalks, street lighting, street trees, and some on-street parking lanes along both sides of Manchester Road.  The contractor is expected to begin this project later this Spring and the project is expected to take approximately 1 year to complete.